Williams Lake Dam Replacement

Location

Williams Lake, Halifax, Nova Scotia

Contact

info@buildns.ca


ANNOUNCEMENTS + UPDATES

May 2026: Public Service Announcement – Temporary Trail Closure

October 2025: Public Service Announcement – Trail Reopened

September 2025: Public Service Announcement – Temporary Trail Closure

March 2025: Public Service Announcement – Temporary Trail Closure

February 2025: Public Service Announcement – Site Preparation

October 2024:  Williams Lake Dam Replacement Announcement


FAQ

A: As part of this project, Build Nova Scotia’s contractor lowered the lake’s water level in June to allow for construction of the dam. This is a common approach for marine repair. Once the coffer dam is in place, the lake level will be 1.54 metres lower than the current lake level.  

When the new dam is in place, water levels will depend on weather conditions.


A: Equipment was mobilized on site in late May to install the coffer dam. This removed water from the construction site and created a dry, safe area that enabled construction of the new dam.

Removal of the old dam began in June and construction of the new dam begins in July.

Pre-construction water and property assessments were carried out, as well as bird and turtle surveys to determine which species live and breed in the area and to ensure they are protected.


A:    Construction of the new dam begins in July and will take approximately two months to complete. We anticipate restoration work will begin this fall, following removal of the coffer dam. This restoration work will include planting trees and cleaning up the trail. The entire project is expected to be complete in spring 2027.


A: The three-year time frame includes both the design and construction of the dam. The design work started in fiscal year 2024/25 and construction is taking place mostly over five to six months, beginning in June, 2026, followed by planting and restoration work. The entire project will be complete by Spring, 2027.


A: The trail to the dam is closed during construction to ensure the safety of both the public and workers on site.


A: No. The parking lot is during construction to ensure the safety of both the public and workers on site.


A: Yes, the McGowan Lake Fish Hatchery continued its annual spring stocking of Williams Lake.  You can find the schedule on the Department of Fisheries and Aquaculture website at Weekly Stocking Update 2026 – Government of Nova Scotia, Canada 


A: The contractor determined when blasting was necessary. When it was required, specific regulations were followed to ensure the safety of people, property and wildlife.


A:  Yes. This activity took just a few weeks and nearby residents were notified.


A: Water samples were taken before construction began and continue to be taken throughout construction. While it is possible water quality may be temporarily impacted downstream during construction, when removing the coffer dam and during dam start up, all work is being done in accordance with detailed environmental regulations that are required when working in or near water. Measures include silt booms that were installed around the site.